Design and drafting can start before take over of the premises, as soon as confirmation of renting / purchasing the premises |
Confirmation of master floor plan is essential, after which all other design work, or renovation work can begin |
Major change of design or completed work items will seriously affect the completion date, and should be avoided |
Project completion can be speeded up by night work, but cost will be raised significantly |
Carpentry work and delivery of tailor made furniture / cabinet are determining procedures, which affect other works and project completion |
Project completion will be significantly affected if management company apply strict limitation policy on noisy work procedures |